Objectives : |
| 1) |
Providing Reliable and Quality Supply. |
| |
|
| 2) |
Meeting Load Growth Demand. |
| |
|
| 3) |
Reduction in Distribution Losses. |
|
| |
|
| |
|
|
| |
MERC in-principle clearance till date (13.12.2007) |
119 Divisions |
|
| |
|
| |
|
|
| |
Project Cost for 119 Divisions (Rs. in Crores.) |
Capital |
R&M |
Total |
6501.48 |
2416.66 |
8918.15 |
|
| |
|
|
|
| |
|
|
| |
Finance : |
PFC:54 Projects amounting Rs. 3767.56 Crores
REC:41 Projects amounting Rs. 2875.45 Crores
Raigad Cooperative Bank:2 Projects amounting Rs. 235.00 Crores |
|
| |
|
|
|
| |
|
|
| |
Major Works to be Carried under Infrastructure Projects (119Divisions) |
33/11 KV Sub-Station (Nos) : |
565 |
22/11KV Augmentation(Nos) : |
30 |
Augmentation(Nos) : |
469 |
Additional Power T/F (Nos) : |
352 |
Switching Stations (Nos) : |
32 |
33KV Line (Kms) : |
7854 |
22KV Line (Kms) : |
4059 |
11KV Line (Kms) : |
41379 |
LT Line (Kms) : |
22890 |
22/0.4 KV DTCs (Nos) : |
5587 |
11/0.4 KV DTCs (Nos) : |
57304 |
HVDC 22KV (Nos) : |
9479 |
HVDC HT Line (Kms) : |
4247 |
|
|
| |
|
| |
 |
|
| |
(Infrastructure Projects will be executed on Turnkey basis) |
|
| |
|
| |
 |
|
Infrastructure Plan Phase- I: |
Estimated Project Cost of 17 Tenders (37 Projects) = Rs. 3057.18 Crores |
| |
|
Letter of award has been issued for 12 Tenders (Click for the details) |
|
| |
|
| |
Infrastructure Plan Phase- II: |
Estimated Project Cost of 53 Tenders (88 Projects) = Rs. 6718.61 Crores |
| |
|
Letter of award has been issued for 7 Tenders (Click for the details) |
| |
|
Status of Tendering process of
Infrastructure Plan Phase - II |
|
| |
|
|